Aligning Retainage with Work Completed

A Milrot Industries viewpoint on reducing retainage as projects progress and releasing funds when subcontractors complete their work.

Read the article

Completing the Work and Receiving Final Payment

In construction, completing the work and receiving the final payment are often two very different milestones.

Retainage has long been used as a financial safeguard for project owners, helping ensure contractors fulfill their contractual obligations before receiving their final payments. Although this practice serves a legitimate purpose, it can also create unnecessary financial pressure on contractors and subcontractors who have already completed their work.

Consider a subcontractor who finishes their entire scope within the first six months of a two-year project. Under certain contractual arrangements, that subcontractor could be required to wait another 18 months to collect the money they have already earned.

At Milrot Industries, we believe retainage remains an important part of construction contracting. However, we also believe there is an opportunity to reconsider how much is withheld, when it should be reduced, and when those funds should be released.

Understanding Retainage

Retainage is a percentage of money withheld from a contractor's progress payments to provide financial protection to the owner. It helps ensure that contractual obligations are satisfied, incomplete work is addressed, and the project reaches an acceptable level of completion.

On projects where a 10% retainage rate is used, a contractor billing $100,000 for completed work would receive $90,000, with the remaining $10,000 withheld.

That retainage may not be released until substantial completion or another milestone established by the contract.

The arrangement frequently extends beyond the general contractor. When an owner withholds retainage from the general contractor, the general contractor may withhold a corresponding percentage from its subcontractors.

The result is a payment structure in which the financial burden extends down the construction chain.

Although 10% remains a familiar contractual starting point in some markets, retainage requirements differ by jurisdiction and project type. For example, Florida law generally limits retainage on covered public construction contracts to 5% (Florida Legislature, 2026).

Owners deserve financial protection throughout construction. However, maintaining the same retainage percentage for the entire duration of a project may not always be necessary, particularly when substantial portions of the work have already been completed and accepted.

Reducing Retainage at Halfway Completion

Consider a $10 million commercial construction project operating under a 10% retainage agreement.

By the time the project reaches 50% completion, assume the contractor has completed and billed $5 million worth of work.

Under the existing agreement, approximately $500,000 would have been withheld in retainage.

At Milrot Industries, we believe this is an appropriate point to reconsider the amount being held.

If the project is progressing satisfactorily, the owner could reduce the accumulated retainage from 10% to 5%, releasing $250,000 to the contractor. Future progress payments could also be subject to the reduced 5% withholding.

The owner would still maintain meaningful financial protection, while the contractor would recover a substantial amount of working capital.

This isn't an entirely new concept. The AIA-MBA Joint Committee's construction best-practices guidance recognizes reducing retainage from 10% to 5% at the halfway point of a project (AIA-MBA Joint Committee, n.d.).

However, reducing retainage at the project level only addresses part of the issue.

Subcontractors who complete their work early in the construction schedule may still have substantial amounts of money withheld long after their contractual responsibilities have been fulfilled.

Two hard-hat construction professionals beside a half-built commercial building, a halfway progress gauge and retained coins divided between protection and release.
Conceptual illustration: balancing retained protection with access to working capital as work progresses.

Six Months of Concrete Work and an Additional 18 Month Wait

Consider a two-year commercial construction project with a concrete subcontract valued at $500,000.

The concrete subcontractor begins working early in construction and successfully completes their entire scope within the first six months.

Assume all required inspections are approved, contractual documentation is submitted, and the work is accepted.

Under a 10% retainage agreement, the concrete subcontractor would have accumulated $50,000 in withheld payments.

Now assume the contract requires that money to remain withheld until the overall project is completed.

The concrete subcontractor could be waiting an additional 18 months to collect $50,000 for work that was already completed and accepted.

During those 18 months, the subcontractor still has obligations to meet. They must pay employees, purchase materials for future projects, maintain equipment, cover insurance costs, and fund everyday business operations.

Meanwhile, $50,000 of their earned revenue remains unavailable.

We believe there is a more financially responsible approach.

Rather than tying the concrete subcontractor's retainage to the substantial completion of the entire building, contracts could establish provisions allowing retainage to be released once the subcontractor's specific scope has been completed and accepted.

There would still need to be safeguards addressing defective work, outstanding documentation, unresolved claims, and any required surety approvals. However, these concerns could be addressed through an appropriate closeout process rather than automatically withholding the entire amount until the project ends (American Institute of Architects, 2025).

A subcontractor's payment schedule should reflect the completion of their contractual responsibilities, not necessarily the completion of everyone else's.

A concrete subcontractor with a completed-work checklist beside a finished foundation, while a locked coin jar, hourglass and calendar pages represent delayed funds.
Conceptual illustration: a subcontractor can finish their scope while retained funds remain unavailable.

The Financial Cost of Withheld Retainage

There is another financial consideration that deserves attention: the time value of money.

Returning to our concrete subcontractor, assume the $50,000 remains withheld for 18 months after their scope is completed.

If the party controlling those funds placed the money into an interest-bearing account earning an illustrative 4% annually, the interest accumulated over those 18 months would be approximately $3,000 using simple interest.

The calculation is straightforward:

$50,000 × 4% × 1.5 years = $3,000

Now consider the subcontractor's perspective.

If the subcontractor needed to borrow that same $50,000 through a line of credit at an illustrative 10% annual interest rate, maintaining that balance for 18 months would result in approximately $7,500 in interest expense using simple interest and excluding fees.

$50,000 × 10% × 1.5 years = $7,500

That's a potential $7,500 financing expense simply because the subcontractor did not have access to money associated with work they had already completed.

These figures are hypothetical. Retainage does not automatically earn interest for the owner or general contractor, and subcontractors do not necessarily need to borrow the entire withheld amount. Actual results depend on who controls the funds, contractual requirements, interest rates, and financing arrangements.

Nevertheless, the example illustrates an important financial imbalance.

One party could potentially earn interest on retained funds while another incurs borrowing costs to compensate for the same amount being unavailable.

Industry guidance from the Associated General Contractors of America, American Subcontractors Association, and Associated Specialty Contractors recommends considering interest-bearing escrow arrangements that benefit contractors and subcontractors in their respective shares (2008).

The interest itself is not the largest concern. The greater concern is the financial burden placed on contractors who must wait extended periods to receive money they have already earned.

Our Perspective on Retainage and Performance

At Milrot Industries, we believe retainage should remain a tool for protecting project performance rather than unnecessarily restricting contractors' working capital.

We recognize that owners have legitimate financial concerns. Construction projects carry risks, and releasing money too early without adequate protection can create additional exposure.

However, retainage provisions can be structured around measurable performance.

Reducing retainage when a project reaches 50% completion, provided the work is progressing satisfactorily, is one opportunity.

Releasing retainage to subcontractors upon the accepted completion of their individual scopes is another.

Both approaches would require clearly established contract provisions, appropriate documentation, and compliance with applicable payment laws.

These changes wouldn't increase the amount a contractor earns under their contract.

They would simply allow contractors to access their earnings sooner.

As we discussed in our first publication on billing lags, profitability and liquidity are not the same thing. A company can be profitable while still experiencing cash-flow difficulties.

Retainage can contribute to that challenge, particularly when substantial sums remain withheld long after a subcontractor has finished working.

Retainage should serve as financial protection for project owners without unnecessarily restricting contractors' access to earned revenue. By aligning retainage reductions and releases with actual work completed, the construction industry can better balance financial security with the cash-flow needs of contractors and subcontractors.

As Milrot Industries continues its journey, we look forward to exploring ideas like these, asking questions, and learning from the professionals who help shape the construction and logistics industries.

Thank you for reading, and we look forward to continuing the conversation.

— Milrot Industries

References

AIA-MBA Joint Committee. (n.d.). Contracts: Section D-5, retained percentage. https://aiambajointcommittee.org/contracts/

American Institute of Architects. (2025). Instructions: A401–2017, standard form of agreement between contractor and subcontractor. AIA Contract Documents. https://acdoperations.zendesk.com/hc/en-us/articles/1500009803382-Instructions-A401-2017-Standard-Form-of-Agreement-Between-Contractor-and-Subcontractor

Associated General Contractors of America, American Subcontractors Association, & Associated Specialty Contractors. (2008). Guidelines for a successful construction project (Guideline D.3.k, Retainage). https://www.consensusdocs.org/wp-content/uploads/2022/11/Guidelines-for-a-successful-construction-project.pdf

Florida Legislature. (2026). Florida Statutes § 255.078: Public construction retainage. https://www.flsenate.gov/Laws/Statutes/2026/255.078

Related service context · All posts

Join the conversation

Your perspective matters.

Have a different experience or a useful question? Share it below. Comments and replies appear after review.

Loading discussion…

Leave a comment

Up to 2,000 characters. Keep it relevant and respectful. Do not include contact details or confidential project information.

Display names are reader-supplied, not verified identities. Likes reflect browser reactions, not verified individuals.